By Maggie Beamguard
The first phase of construction on the Lake Sequoia dam project is progressing. Initial site preparation is complete, and materials for the installation of the new siphon system are staged.
Heather Guild, the Seven Lakes Landowners Association board member overseeing the project, said crews completed several infrastructure tasks in September, including building an access road and clearing trees behind the dam and in the area of a new plunge pool. Locations for new piping and culverts were also surveyed.
Phase one of construction involves the creation of the plunge pool. The plunge pool will catch outflow from the new barrel, riser and siphon system. It has been completed and lined with riprap. Erosion control measures have also been installed.
The next phase will be laying pipe at the back side of the dam from the plunge pool to the site of the new drain system. Long-lead precast reinforced concrete (PRC) pipes have been delivered to the site.

Guild said the project team is pleased with their progress. Good communication between contractors and engineers as well as favorable weather have kept the project on track thus far.
While the project remains on schedule, the drawdown of the lake by three feet continues to fluctuate due to weather conditions. Additionally, water crews flushed fire hydrants into Lake Sequoia on two occasions after the drawdown began. Guild estimated that the first incident added approximately 500,000 gallons of water to the lake. The project team will seek better coordination with county water officials.
The road across the dam remains closed to all traffic, including vehicles, golf carts, bicycles, e-bikes and pedestrians. Guild said the closure is necessary to protect workers and the public, as well as construction materials and equipment.
Some residents have taken advantage of the lowered lake level to repair docks and bulkheads. Residents are cautioned against applying chemicals to shoreline vegetation which can harm the lake’s wildlife and plant ecosystem.
The back side of the dam is the current focus. The next major phase will involve the installation of a temporary cofferdam to create a dry work area for construction on the front side. Divers will be employed during the installation of the siphon system during a later phase of construction.
The existing barrel system will remain in use during construction. Once the new system is completed and operational, the existing barrel will be filled and capped.
NCDEQ required the project to provide a way to lower Lake Sequoia on demand to meet dam-safety rules, which took effect in 1979, four years after the dam was built.
Contact Maggie Beamguard at maggie@thepilot.com.